Project name: Caragana Tower Mine and Coal Preparation Plant Project
Construction location: Shenmu County, Yulin City, Shaanxi Province
Project Overview: Nangtiaota Coal Mine is one of the four key mines planned in the southern area of the Shenfu Mining Area of Shaanxi Province among the 13 national coal bases in the Shendong Base,Constructed by Shaanxi Coal Industry Group Co., Ltd.。Today is located in the northwest of Shenmu County, Yulin City, Shaanxi Province,The administrative division belongs to Sunjiacha Town, Shenmu County、Jurisdiction of Majita Township。January 2009,The former Ministry of Environmental Protection issued the "Environmental Review and Change Office [2009] No. 6" document on the "Environmental Impact Report of the Caragana Tower and Coal Preparation Plant (Change) of Shaanxi Coal Group Shenmu M88 loginCaragana Tower Mining Co., Ltd. (Change)" (12.00Mt/a)》Approved; February 2011,The former Ministry of Environmental Protection issued the "Environmental Inspection [2011] No. 36" document on Caragana Tower Mine (12.0Mt/a) The completed environmental protection acceptance report was approved。January 2022,The Shaanxi Provincial Development and Reform Commission approved the increase of Nangtiaota Coal Mine to 20 million tons/year with Shaanxi Development and Transformation of Coal [2022] No. 120。
Construction status: Nangtiaota coal mine field area 119.7735 square kilometers,Adopt inclined shaft development method,Construct a supporting coal preparation plant of the same scale,The coal preparation method is heavy medium shallow tank。Set up mine (including coal preparation plant) industrial site、North wing air shaft site、South wing air shaft site、Waste removal site and blasting equipment warehouse site、Mine four platform site、m88 reviewNorth Wing No. 2 wind shaft site and other venues。Installation of 4 20t/h boilers in the boiler room of the main industrial site of the mine,1 unit 3 installed at the air shaft site in the south wing of the mine.9 electric boiler。
Environmental protection situation:
Ecology: According to the production continuity arrangement and mining progress,Carry out off-site housing resettlement or monetary relocation in advance for the surface villages that will affect the mining of the working face。Carried out greening, tree planting and grass planting on both sides of the off-site road and in the factory area;The waste dump has been covered with soil。
Surface water: A mine water treatment station is located on the main industrial site,Mine water is partially reused after treatment,The remaining portion will be sent to surrounding companies for comprehensive utilization,No discharge。The main industrial site and the four platform sites each have a domestic sewage treatment station,After treatment, all domestic sewage is used as supplementary water for coal preparation plant production and site greening and sprinkling、Dust-proof and water-proof, etc.,No discharge。
Groundwater: The construction unit has formulated a groundwater monitoring plan,Entrust a qualified testing company to conduct regular groundwater testing。
Atmosphere: The flue gas from the coal-fired boiler in the boiler room of the main industrial site adopts the "SNCR denitrification system + bag dust collector + sodium calcium double alkali desulfurization system" treatment process,Raw coal、Product coal adopts closed facilities,Coal processing and transportation system、Atomizing dust collectors are installed at each reprinting point。
Acoustic environment: choose low-noise equipment for the project,To the m88 casino reviewventilation room、Air compressor room、Screening and crushing equipment、The boiler room drum induced draft fan and other high noise sources have adopted sound insulation、Shock reduction、Silent silence and other measures。
Solid waste: digging into the gangue but not out of the well,Wash and select gangue for ditch filling and land construction,Domestic waste and water treatment sludge shall be disposed of by the municipal sanitation department,Mine water treatment station coal slime mixed with coal powder for sale,Boiler ash and desulfurization ash are used as building materials。
2. Scope and main matters of soliciting public opinions
Scope of soliciting public opinions: the public around and around the project industrial site who may be affected by the project construction,Other public and social groups who are concerned about this project、Relevant departments, etc.。
Main matters soliciting public opinions: from an environmental perspective,What environmental issues do you think should be focused on during the operation of this project,What suggestions do you have for the environmental impact assessment of this project,Your suggestions or requirements for environmental protection during the operation period of this project。
3. Methods for the public to submit opinions
In the process of preparing the draft environmental impact report,The public can fill in the construction project environmental impact assessment public opinion form,By phone、Letter、Feedback to the construction unit or evaluation unit via email。The public comment form web link is attached。
4. Contact person and contact information
Construction unit: Shaanxi Coal Group Shenmu Caragana Mining Co., Ltd.
Address: Nangtiao Tower Village, Sunjiacha Town, Shenmu City, Yulin City, Shaanxi Province
Contact: Bai Jian
Tel: 13080986618
E-mail:375797284@qq.com
EIA unit: China Coal Science and Industry Group Beijing Huayu Engineering Co., Ltd.
Address: No. 67 Ande Road, Xicheng District, Beijing
Contact: Zhang Gong
Tel: 010-82276546
E-mail: 870107947@qq.com
Public comment form download address:
http://www.mee.gov.cn/xxgk2018/xxgk/xxgk01/201810/t20181024_665329.html
Shaanxi Coal Group Shenmu Caragana Mining Co., Ltd.
April 29, 2022