Hanjiawan Coal Company: The time taken to hang the net at the end of mining has set a new record
Release time: 2022-05-20     Author: Yang Heng    Views: 11370    Share to:

配图.jpg

Days ago,When the 213108 fully mechanized mining working face of Hanjiawan Coal Company is pushed to the stop of mining and the grid line position,The installation team only took 8 hours,Safely completed the 263-meter network hanging task,The time taken to hang the net at the end of the harvest has set a new record。

As understood,When the 213108 fully mechanized mining working face is pushed to a position of m88 casino30 meters,The installation team of Hanjiawan Coal Company transported the required flexible nets to the return air duct and placed them in advance,Arrange personnel to lay the main air duct of the pneumatic single-arm anchor drilling rig,And leave an air duct interface in the support area。At the same time,Carry out advance maintenance on tools and tools supporting fixed anchor points,Ensure that the supporting equipment is intact and reliable。

When pushing mining to the 10-meter position of the stop line,The installation team laid mining high-strength polyester fiber mesh on the upper part of the bracket。The longitudinal length of the mesh is 267 meters,Width 10 meters,The overall laying work is affected by equipment and working environment,It is difficult to lay,The process is more complicated。

Working site,The installation team divided the personnel into four groups to perform anchor support work,And assign managers above the team leader to be responsible for the safety of each group's operations,Successfully completed m88 sports betting reviewthe support work of 156 anchor points required on the working surface。Follow "Pull the wire rope,Carrying giant flexible net、Zhanwang、hanging network、A series of processes such as "hanging wire rope",Successfully completed the final mining and network task。

Before the last harvest of this time is hung up,The installation team will reinforce the coal wall area in advance,Conscientiously implement the Internet security technical measures for non-adopted products,Response to air leakage from air duct interfaces on site、Many hidden dangers such as coal wall patch gangs will be investigated and rectified in a timely manner,Ensure the safety and reliability of the work site,Lay a solid foundation for the successful completion of the retracement task。(Author: Yang Heng  Editor: Wang Yu)