Release time: 2022-09-02     Author: Wang Yu Meng Aman    Views: 12000    Share to:

       Recently,Shaanxi Coal and Shaanbei Mining Sunjiacha Longhua Coal Mine has stopped production for maintenance,The maintenance task originally planned to be completed in 20 days,It only took 16 days to complete successfully,Exactly 4 days ahead of schedule。

m88 casino review

Longhua.png

Sunjiacha Longhua Coal Mine was established in 2008,The original design annual production capacity was only 600,000 tons。2021,Coal mine production capacity increased to 10 million tons。Production has increased,But production、Transportation、Wash selection、Power supply and other systems,But it has become a bottleneck restricting the high-quality development of coal mines。

For this,Longhua Coal Mine has upgraded and transformed coal mine production as early as the production increase、Auxiliary system work is on the agenda。“This overhaul and system transformation,Time is tight、Heavy task,Managers at all levels must fulfill their duties,Strive to complete the maintenance and system transformation tasks ahead of schedule。" Longhua Coal Mine Director Cao Guoxuan said at the maintenance mobilization meeting。

After the meeting,Relevant departments take quick action。Check device status、Contact the construction team、Planning renovation plan、Prepare maintenance plan、Purchase equipment and materials、Develop safety measures,Clear division of labor among cadres and workers、Everyone performs M88 gamehis own duties、Organized。

During this period,Many managers voluntarily give up their vacation,Insist on eating and living in the mine。dormitory、Canteen、Maintenance site,Three points and one line is their true portrayal。“Such a living situation,Just enough to help me lose weight。" one manager said jokingly。

When carrying out technical transformation of the washing system,Need to pair 3 units of 26 tons、A 20-ton vibrating screen is dismantled。The demolition task was originally planned to take 5 days to complete,Due to sufficient preparations,It took only two and a half days to dismantle everything,Won valuable time for maintenance。

Conductor: coordination, strength and dedication

Longhua Coal Mine is shut down for maintenance this time,This is the largest overhaul since the mine was built,Total production、Transportation、Power supply、Wash and select 127 items of various sizes。Involving 11 district teams,13 professional installation teams,More than 600 maintenance personnel,Production Organization、Measure execution、Security management is more difficult than ever。

“We adopt a grid-based guarantee management method,Divided guarantee areas for leaders and managers at all levels,Clear division of responsibilities。" said Liu Haisheng, director of Longhua Coal Mine Dispatch Center。

Initial stage of production shutdown and maintenance,Due to the impact of the epidemic,Many professional installation teams cannot arrive on time、Equipment and supplies cannot arrive in time,M88 loginAffected the maintenance progress。To this,Longhua Coal Mine adopts cross operation、Concentrated attack measures,Gather the power of the whole mine to promote the orderly implementation of maintenance work。

At that time,The most interesting situation is,You are working in this district team today,I may go to work in another district team tomorrow。Although it is very hard,But for a common goal,Workers readily accepted,No complaints。

Yang Xiaoli, chief engineer of Longhua Coal Mine,Insist on on-site surveillance during maintenance,Wherever there are difficulties, there is his presence。But he said: Others have harder work than me。

Together: Unity and one heart

As long as your mind is thinking in one place、Use your energy in one place,There is no mountain that is insurmountable、There is no river that cannot be crossed,This is the deep-seated reason why Longhua Coal Mine shut down production and overhaul successfully。

“This production shutdown and maintenance was a complete success,Inseparable from the leadership’s advanced decision-making,Inseparable from the front-line command of the management,It is inseparable from the hard work of the majority of cadres and workers。" Zhang Jinbo, deputy director of Longhua Coal Mine, said。

During shutdown for maintenance,Centers of various departments、The district team workshop separately formulated a "Roadmap" and "Construction Schedule",Inverted schedule,Do a good job in manpower、Material resources and related support work。The majority of cadres and M88 gameworkers strictly follow the time nodes,Complete the amount of maintenance tasks with quality and quantity。

At the same time,A large number of advanced model figures have emerged。Li Jiang, deputy chief of the Mechanical and Electrical Department,Send honeymoon wife back to her parents’ home,Stick to the front line of maintenance。Zhang Jibo, first-level business manager of the Planning and Development Department,Being responsible for the renovation and renovation of Longhuafu Hotel,I have to be responsible for production shutdown and maintenance tasks again...(Wang Yu Meng Aman)