The installation task of 2205 intelligent working surface was successfully completed
Release time: 2023-11-08     Author: Cui Tianxin Xie Wenhao    Views: 2716    Share to:

11.jpg

Recent, Zhangjiamao Mining Company urgently starts the 2205 intelligent working face installation project,After receiving the installation task,The Zhangjiamao Intelligent Maintenance Center of the Information Technology Operation and Maintenance Branch immediately organized all personnel to hold a mobilization meeting for the installation and implementation of the work surface,Emergency deployment of "combat" plan based on actual situation。

The center’s M88 appprimary responsibility is to ensure the mine’s annual production tasks,Actively set up a special working team for this difficult task,Quickly formulate eight points、Cooperative installation plan for two shifts at four o'clock,And went all out to carry out preliminary equipment preparation and debugging work,And completed the installation task within three days,Refreshed the record for the fastest retracement of working surface installation。

Period,After the installation team of the center entered the well in different shifts,Start laying communication and power cables on the 2205 working surface according to scheduled groups。At the same time,Converged communication and video service operation and maintenance personnel go to the work surface and console location,Start installing the converged base station、Broadcast、Power supply、Locating substations and cameras and other equipment。

The installer will deploy the well-configured system communication equipment at the rear of the 2205 working surface as required,Promote bracket fixation in an orderly manner、Laying M88 gameterminal equipment power cables、Installation of supporting power supply and UPS backup power supply,Model head installed、Tail and console telephone equipment,Completed the splicing of the backbone optical fiber link and the console video switch、Debugging of wireless base stations and industrial control switching equipment。Install broadcasting in the 2205 nose and console area、Power supply、Positioning and other equipment,Region-wide broadcast、Telephone、Positioning、Wireless communication、Function and stability testing of industrial control and other systems。After all test results are normal,Organized and implemented the standardization work of all equipment and cables。

final,The center successfully completed the installation of the working surface,Ensure that the 2205 working surface is put into production on schedule,Provides strong technical support for mine safety production。(Cui Tianxin Xie Wenhao)