This year,Shennan Mining Company actively implements the "1116" work idea of Northern Shaanxi Mining Company,Firmly seize the adjustments and opportunities in the coal industry policy of Zhongzhou Province,Work hard to coordinate、Steadyly promote the processing of "five key procedures",In turn, it will drive resource development、The overall work of resource mergers and acquisitions is advanced in an orderly and efficient manner,So far, certain progress has been made in all key tasks of the year。
First, steadily promote the reserve review and filing work of Xiaohaotu No. 3 well field (western exploration area),This procedure has now completed the on-site verification and report review work of the Shaanxi Provincial Department of Natural Resources。
The second is to steadily promote the "exploration-to-mining" procedures for the Xiaohaotu No. 1 Coal Mine Project,This procedure has now M88 logincompleted the review of the mineral resources development and utilization plan。
The third is to steadily advance Xiaohaitu No. 1、Retention of No. 3 (Western Exploration Area) Exploration Rights,This procedure has currently obtained the verification opinions agreed to be retained by the Yulin Municipal Administrative Approval Bureau and the Yuyang Branch of the Yulin Municipal Natural Resources Bureau,The next step will be reported to the provincial department for verification。
The fourth is to successfully transfer Xiaohaitu No. 1、No. 3 coal mine project was incorporated into Yulin City、Key construction projects in Yuyang District,At the same time, we are also closely following up and coordinating the inclusion into the key projects of Shaanxi Province’s “15th Five-Year Plan”。
The fifth is to steadily advance Yushen III、Phase IV mining area planning and planning environmental impact assessment work,The Energy Bureau of the National Development and Reform Commission has organized an evaluation of the overall plan of the Yushen Phase IV mining area,Currently being modified and improved。(Xu Hailong Quan Zelin)